How single estimate accounts for different ability of each team member? E.g. Somebody new joining in will need more time.
replies(1): >>crazyg+b1
2. crazyg+b1[view] [source] 2026-01-24 22:15:21
>>lucket+(OP)
Estimates are for the team, not for an individual.

As the team grows and shrinks, the number of points delivered per sprint are expected to similarly rise and fall. A new person joining will likely take time to ramp up the number of points they're contributing.