1. post_f+(OP)[view] [source] 2022-01-28 05:49:08
It took us NINE MONTHS to get a server installed in a data center a few years back. This was Marine-Corps fielded hardware running an ATO'd[1] software stack for real-world situational awareness, going into a Marine Corps data center. The people that run the data center have a glacial Change Management process, exacerbated by everyone in their organization not talking to each other, even though they are separated by cubical walls.

I too have no faith of seeing this stuff implemented anytime soon...

[1] (Authority to Operate, basically approval from the highest IT authorities to utilize something on a DoD network)

replies(1): >>warner+Z3
2. warner+Z3[view] [source] 2022-01-28 06:26:49
>>post_f+(OP)
Haha, yes, my day-to-day work for the past two years has been fighting exactly this same fight on the Army side.