If true - how fast could a new transmission line from France to Germany pay for itself?
Germans would get the full cost which is much higher than the quoted price here. Besides nuclear power is not flexible enough to amp it up and down according to demand (unlike coal or petrocarbon industries).
TLDR More interconnector capacity, battery storage, and renewables needed (my analysis).
[1] https://www.oecd-nea.org/upload/docs/application/pdf/2021-12...
[2] https://app.electricitymaps.com/zone/FR?wind=false&solar=fal...
[3] https://www.euractiv.com/section/coal/news/france-extends-li...
Nuclear reactors are already very cost ineffective when used as baseload. Theyre ridiculously cost ineffective when used for load following since it's basically curtailment.
This is why most countries tend to use gas or hydro/pumped storage for load following (or, increasingly, batteries as theyve been plummeting in price).
Ontario, Canada would disagree with you: nuclear is 10.1¢/kWh, hydro is 6.2¢, (methane/natural) gas is 11.4¢; see Table 2:
* https://www.oeb.ca/sites/default/files/rpp-price-report-2023...
Of course hydro-electric dams typically flood many hectares of land for the reservoir. The current ones are getting refurbished:
* https://www.cbc.ca/news/canada/toronto/niagara-ontario-power...
Ontario's nuclear fleet are also in the middle of a bunch of refurbs:
* https://www.cbc.ca/news/canada/toronto/ontario-nuclear-power...
Some of which are finished:
* https://www.opg.com/releases/opg-celebrates-the-early-comple...
Live data on Ontario's grid:
* https://ieso.ca/power-data § "Supply" tab