Not a single mention of planning poker and story points?

They're not perfect (nothing is), but they're actually pretty good. Every task has to be completable within a sprint. If it's not, you break it down until you have a part that you expect is. Everyone has to unanimously agree on how many points a particular story (task) is worth. The process of coming to unanimous agreement is the difficult part, and where the real value lies. Someone says "3 points", and someone points out they haven't thought about how it will require X, Y, and Z. Someone else says "40 points" and they're asked to explain and it turns out they misunderstood the feature entirely. After somewhere from 2 to 20 minutes, everyone has tried to think about all the gotchas and all the ways it might be done more easily, and you come up with an estimate. History tells you how many points you usually deliver per sprint, and after a few months the team usually gets pretty accurate to within +/- 10% or so, since underestimation on one story gets balanced by overestimation on another.

It's not magic. It prevents you from estimating things longer than a sprint, because it assumes that's impossible. But it does ensure that you're constantly delivering value at a steady pace, and that you revisit the cost/benefit tradeoff of each new piece of work at every sprint, so you're not blindsided by everything being 10x or 20x slower than expected after 3 or 6 months.

◧◩
2. Fire-D+3u1[view] [source] 2026-01-24 21:52:54
>>crazyg+Ae1
Because story points MUST be specific per person based on the smallest task they ever faced, they cannot be summed up because they are not units, and points do not translate to time, we cannot talk about story points.

Sorry if it comes through as rude, but this is how I keep repeatedly being told story points work.

If you look at all those properties together, story points are completely useless.

The only moment time it makes sense is when you have a SHARED understanding of the smallest point AND you can translate it to time. When you do that, story points are useful. Also, they become time, so there is no reason to use points.

◧◩◪
3. bogeho+vv1[view] [source] 2026-01-24 22:02:40
>>Fire-D+3u1
> The only moment time it makes sense is when you have a SHARED understanding of the smallest point AND you can translate it to time. When you do that, story points are useful.

I’d like to disagree on that one. A single story point shouldn’t be translated to time, but should reflect the relative complexity between tasks (ie. a 7 is harder than a 3 and so on).

You could assign relative complexity based on a number of things:

- number of integrations to other systems, - is the area well known to the team, - is the code well tested, - is CI/CD set up, - do we need a lot of alignment or can we just get started, - etc.

So you’re not estimating time, but complexity or hardness.

Then, supposing you have a stable team, you can go back six months and find out “we do on average 90 points per month” or similar