1. xnx+tc[view] [source] 2025-05-13 21:32:12
>>wiley1+(OP)
Can this possibly make financial sense even if launch costs were zero?

One NVIDIA DGX SuperPOD consumes 10 kW which would be ~500 square feet of solar panels and ~100 square feet of radiator area.

◧◩
2. transp+Df[view] [source] 2025-05-13 21:50:04
>>xnx+tc
https://www.thetimes.com/business-money/companies/article/th...

> Their design calls for a cluster of shipping container-style boxes packed with high-speed AI chips. These would be anchored at the centre of a 16 sq km array of solar panels generating up to five gigawatts of power — about 25 per cent more than Drax, Britain’s biggest power station. The mammoth structure would circle the Earth in “sun synchronous” orbit so that it is never in shade

◧◩◪
3. semi-e+tm[view] [source] 2025-05-13 22:42:09
>>transp+Df
Their whitepaper clearly demonstrates a profound lack of knowledge of thermal engineering. E.g. heat pumps are described as magical things.

They are literally planning to feed the radiators using a coolant like water and sensible heat at 35 degC to 5 degC. At 5 GW, you then need to be pumping 60 000 liters of water per second.

That's like a tenth of the Sacramento river, going through a 16 sq km array in space and hoping that nothing leaks.

◧◩◪◨
4. xnx+es[view] [source] 2025-05-13 23:19:50
>>semi-e+tm
> 60 000 liters of water per second

Then they just need to worry about the extra friction heat generated by moving that much liquid.

◧◩◪◨⬒
5. ceejay+Nt[view] [source] 2025-05-13 23:30:41
>>xnx+es
And what happens if there’s a power outage. Frozen pipes aren’t all that fun.