1. ZeroGr+k8[view] [source] 2023-01-12 19:48:13
>>RobinL+(OP)
Curtailment, like negative prices, seems like something that it is hard for people to have constructive conversations about.

Probably the cheapest and best option is to build more wind and not care too much if it increases curtailment.

Yes, all the things mentioned should be looked into and done when it makes financial sense but "wasting wind" is much less a thing to worry about than "burning gas", and I'd rather waste wind than waste money.

◧◩
2. redlea+ud[view] [source] 2023-01-12 20:13:19
>>ZeroGr+k8
Balancing a nationwide power grid is very complex. Some energy sources can be started and stopped instantly, but are limited - water. Others are plentiful, but unpredictable - wind. Others are predictable, but take a long time to start and stop - gas, coal(several hours), nuclear(1 day to start, fast to stop, but very expensive). A balanced grid will need all of them, will need them in quantities which can cover faults in the big producers(a nuclear reactor makes 700-800 MW). They will need them built in the right place, because while more power cables can be built, you can't transfer a lot of power on very long distances, for cost and grid stability reasons.
◧◩◪
3. Reason+On[view] [source] 2023-01-12 21:08:40
>>redlea+ud
> "(a nuclear reactor makes 700-800 MW)"

1.6 GW per reactor for the latest ones under construction (Hinkley Point C) and in development (Sizewell C). Each site has 2 reactors for a total of 2 x 2 x 1.6 GW = 6.4 GW.

Although this is largely just replacing the UK's existing fleet of reactors, almost all of which will have shut down by the time Hinkley Point C comes online. Of the current 5 operating UK nuclear power stations, only Sizewell B is scheduled to operate beyond 2028.

> "They will need them built in the right place, because while more power cables can be built, you can't transfer a lot of power on very long distances"

One of the reasons offshore wind has been so economic & successful in the UK is they can usually plug in to existing, redundant transmission lines left behind by decommissioned coal and nuclear power stations, which are often on the coast. It's relatively cheap to connect to the grid when the infrastructure is already there waiting: you just need to build the cables from the turbines to the shore.